Progress Update: Gokhale Bridge Work in Andheri Nears Completion

The Gopal Krishna Gokhale Bridge in Andheri is undergoing significant progress with the recent completion of the relocation of a 90-meter-high girder on the southern side. The girder, which was successfully moved on September 8, 2024, will now be brought down to a height of 8 meters from its current 90 meters. This development marks a crucial step forward in the construction of the flyover that serves as a vital link between the western and eastern sides of Andheri.

Major Milestones Achieved

On September 4, 2024, the girder on the railway section of the bridge was lifted to a height of 25 meters. Over the course of the next five days, it was further raised by an additional 65 meters. These intricate procedures were carefully overseen by Bhushan Gagrani, the Commissioner and Administrator of the Brihanmumbai Municipal Corporation (BMC), ensuring the safety and efficiency of the operation.

The challenging task of launching the girder on the south side of the Gokhale Bridge was successfully completed up to a height of 65 meters on the night of September 8, 2024. Despite facing obstacles such as train traffic and power interruptions, the project team effectively resolved these issues to progress smoothly towards the completion of the bridge. The project is being managed by M/s RITES Limited, with the design approved by the Western Railway Authority, ensuring compliance with safety standards and regulations.

Next Steps in the Project

The focus now shifts towards lowering the southern iron beam, currently positioned 14 to 15 meters above ground, to the east side of the railway track. Once the beam reaches a height of 8 meters, it will be supported by RCC columns, marking a unique construction process in India. Following the successful positioning of the beam, additional tasks such as lane markings, installation of streetlights, and road surface improvements will be carried out to enhance the functionality and aesthetics of the bridge.

The Brihanmumbai Municipal Corporation (BMC) has issued a statement indicating that construction activities will continue with the approval of the Western Railway. Collaboration between the BMC and Western Railway remains pivotal in ensuring the timely and effective completion of the Gokhale Bridge project. The first phase of the bridge has already been completed and opened to traffic on February 26, 2024, showcasing significant progress in improving connectivity and infrastructure in Andheri.

Moving forward, the project team is focused on installing the second beam of the bridge, with the aim of completing the second phase by November 14, 2024. This ambitious timeline underscores the commitment of all stakeholders involved in the project to deliver a modern and efficient infrastructure asset for the residents and commuters of Andheri.

Conclusion

The ongoing work on the Gokhale Bridge in Andheri represents a significant infrastructure development that will enhance connectivity and ease traffic congestion in the area. The successful completion of key milestones such as the relocation of the girder and the upcoming installation of the second beam demonstrates the dedication and expertise of the project team. With continued collaboration between the BMC, Western Railway, and other stakeholders, the Gokhale Bridge project is on track to be completed within the specified timeline, offering a vital link between the eastern and western parts of Andheri.