Mumbai construction sites face noise checks, with work to stop over limits

The Bombay High Court has ordered routine, zonal monitoring across the city and said construction must stop where noise exceeds prescribed limits.

Mumbai construction sites face noise checks, with work to stop over limits Rajkumarrr comics

Construction sites across Mumbai must be monitored routinely, and work must stop wherever noise exceeds prescribed limits, the Bombay High Court said on Wednesday. The direction places responsibility on the Brihanmumbai Municipal Corporation (BMC), police and district authorities to check sites across the city, rather than focus on a single building.

The court clarified that it was not ordering a blanket halt to construction. It said authorities must ensure noise remains within the prescribed threshold and take action when it is crossed. For people living near building work, the order sets out a city-wide monitoring requirement, not just a response to complaints about one project.

Mahim case prompted the direction

The bench of Chief Justice MC Tripathi and Justice Advait Sethna was hearing a petition by Ashok Pathare, who lives at Shreyas Apartment on Mogul Lane in Mahim West. His petition concerns construction by Yashodhan Tower LLP on an adjoining plot. Police readings taken on September 15 recorded noise above 100 decibels.

The BMC issued a stop-work notice on September 22 and withdrew it on October 1, citing air-pollution mitigation measures. The civic body issued a fresh notice on October 30; Pathare told the court work had remained suspended since then. The court was also told that police had issued a show-cause notice and the Maharashtra Pollution Control Board had issued a caution notice.

The developer’s lawyer said the project was a self-redevelopment scheme and that 14 other projects were under way within 200 metres. He said the developer would submit an undertaking.

Undertakings and follow-up

The judges said the BMC should not permit construction unless developers filed an undertaking on affidavit that they would comply with noise rules and would not cause air pollution. Further work at the Mahim site can be permitted only after the authorities are satisfied with the undertaking.

Officials have been directed to monitor sites routinely on a zonal basis. The court warned that officials would be held accountable if noise levels did not come down, and said it would review the matter every three weeks. The prescribed noise threshold and a detailed monitoring schedule have not been specified in the report of the hearing.

This report draws on information from The Times of India and Urban Acres.

Editorial checks passed Facts, figures and quotes checked against 2 sources

Add Mumbai News as a preferred source on Google

Related stories