Kalachowki redevelopment: Bombay HC says homebuyers cannot wait indefinitely

The court upheld the BMC’s termination of Om Shanti Properties’ project appointment after 181 residents waited nearly 18 years for redeveloped homes.

Kalachowki redevelopment: Bombay HC says homebuyers cannot wait indefinitely – Mumbai Rajkumarrr comics

In Kalachowki, the Bombay High Court has upheld the BMC’s termination of Om Shanti Properties’ appointment to redevelop a housing property, saying residents cannot be made to wait indefinitely for their homes. The project affects 181 members of Parijat Co-operative Housing Society, who have been waiting nearly 18 years.

A bench of Chief Justice MC Tripathi and Justice Advait Sethna dismissed the developer’s petition challenging the Brihanmumbai Municipal Corporation’s decision to terminate its Letter of Intent (LOI). In its order, pronounced on October 26, the court said developers have a legal responsibility to deliver flats within a reasonable time.

The ruling matters to residents awaiting redevelopment in Mumbai because it backs the society’s ability to move on from a developer that did not meet project commitments. The court said residents “cannot be compelled to continue” with an erring developer indefinitely.

Why the BMC ended the appointment

The BMC first issued an LOI for the property, in Mazgaon Division’s Sanaswadi area, on April 10, 2008. After years of inaction, it issued a show-cause notice in 2017 and terminated the LOI in July 2018. New partners took over Om Shanti Properties later that year, paid Rs 27.68 crore in capital value and obtained a revalidated LOI.

The developer undertook in December 2020 to complete the project by April 9, 2022, failing which the LOI would be automatically terminated. It received an Intimation of Disapproval in April 2021, but did not secure a Commencement Certificate, provide transit rent or carry out physical work at the site, the court noted. The BMC issued another show-cause notice in April 2023 and a final termination notice on February 11, 2025.

Who will take the project forward?

The society ended its agreement with Om Shanti Properties on December 30, 2025, and appointed Tribecca Creators LLP as the new developer on September 8, 2026. The court also noted that the petitioners had not disclosed their 2020 undertaking and ongoing arbitration proceedings when challenging the BMC’s action.

The order described prolonged redevelopment delays as worsening residents’ plight and frustrating the purpose of municipal regulations. The next steps and a completion timetable for the project have not been announced.